A Fargo contractor's $292.4 million bid is the low one for Sioux City's wastewater plant
The Daily Sioux City team
If you've wondered what rebuilding the wastewater plant will cost, there's a new number. The city received three bids for Phase 1, from $292.4 million to $322.7 million, all below the engineer's $325 million estimate. PKG Contracting of Fargo, North Dakota, submitted the low bid, $32.6 million under that estimate, and the Sioux City Journal says the city received a $292.4 million low bid from a North Dakota contractor.
All three bids came in under the engineer's estimate
Three bids for Phase 1 of the wastewater plant improvements
Source: KCAU 9 News
View as table
| Value | Against Engineer's estimate | |
|---|---|---|
| PKG Contracting (Low bid) | $292.4M | $32.6M under |
| Rice Lake Construction | $308.6M | $16.4M under |
| Hawkins Construction | $322.7M | $2.3M under |
- Recommendation: award PKG the base contract, reject all bid alternates
- Next step: the City Council still has to consider the award
- Spread: the three bids landed within 9% of each other
- July: the city declined the Guaranteed Maximum Price it was offered
Hazen and Sawyer, the city's engineering consultant, made the recommendation after reviewing the bids and contractor qualifications. The council earlier voted to cancel its $467 million contract with Kiewit Infrastructure, and council member Rick Bertrand called the re-bid a "solid process."
$32.6 millionunder the engineer's estimate for PKG's low bid
The project budget will also include engineering services, construction oversight, contingency funding, and other project costs.
Source: KCAU 9 News